Highlights Of What We Accomplished Since The Last Update


  • Saturday, February 22nd
  • Team workday at the solar car shop – Jake, Tommy, Ben, Ryder, and Charles met with Shannon, Brian, Mark, and Charlie and continued construction on the new car (see photos below).
  • Jake worked on completing the mechanical CAD drawings
  • Unloaded and set up the 8’ press brake and pipe bender that Mark is loaning us.
  • Press broke, match drilled, and installed the RivNuts for the front right hand side outer crush zone structure
  • Sunday, February 23rd
  • Team workday at the solar car shop – Jake and Langan met with Shannon, Brian and Mark and continued construction on the new car (see photos below).
  • Jake continued working on completing the mechanical CAD drawings
  • Press broke, match drilled, and installed the RivNuts for the front left hand side outer crush zone structure